Midway through February, the deck removal was completed. The crew cut the pipes that lead to the pool filter room and prepared to cut into the side of the pool to place a drain in the wall.
During February, the new gutters were also delivered. The pool was cleaned to prepare for gutter installation. The project remains on schedule.